CodiNetX

Skip Navigation LinksLocally Managed Road Projects

  
Project Description
  
  
Monthly Updates
  
  
  
  
  
  
  
  
  
  
  
  
  
Sum= $45,369,440.00
ST-257

Road Extension

​Carver Street
$7,268,500.00

PW: Carver Street Extension is open to traffic.

Nov 2013Mar 2015Sept 2015Sept 2016Oct 2019Construction100Ed Venable
  
Venable, Ed3.011/4/2019 1:17 PM
ST-264

Road Widening

​Fayetteville Rd: Barbee to Riddle
$12,260,000.00
PW: The work continues for debris removal, signal work, hauling in borrow, grading and storm drainage installation.

RE: All properties (37 in total) are now owned by the City. RE and CAO will work together on mediation/settlement of condemnation suits filed. Timeline for beginning of mediation is early February.
March 2016Dec 31, 2018 (July 2018 )July 2018 (Feb 2018)Feb 2019 (Oct 2018) Oct 2020 (April 2020)Construction10Ed Venable
  
Venable, Ed3.011/4/2019 1:19 PM
ST-271

Petition Street 2017

Ardmore Dr, Castell Dr, Missell Ave, Windburn Ave,
PW: Punch lists are being prepared for Missell Ave and Ardmore Dr. Castell St. has begun construction.

May 20175/23/2018Sept 2018May 20192020-03Construction50Clint Blackburn
  
Venable, Ed3.011/4/2019 1:24 PM
U-5823

Road Extension

Woodcroft Parkway Extension:  Hope Valley Rd. to Garrett Rd.
$4,217,100.00

Contract negotiation and execution has been delayed due to staff vacancies.  Manday Hours/Rates estimates were returned for corrections and have been re-sent to NCDOT for review.  

Revised Manday Estimate and Scope submitted by RKA.

Draft contract sent to RKA. 

2020-122021-052021-082022-032025-08Planning90 %Brian Taylor
  
Beckmann, Ellen3.011/4/2019 2:47 PM
C-5605H

Downtown Durham ​Wayfinding Program

Various Locations within Downtown Durham
$695,750.00

Construction Authroization received September 30. Transition meeting with General Services on Oct. 23. 

2019-09 *** Dates previously adjusted from 2019-07*** 2019-10 *** Dates previously adjusted from 2019-08 ***2019-12 *** Dates previously adjusted from 2019-10***2020-01 *** Dates previously adjusted from 2019-11 ***2020-12 *** Dates previously adjusted from 2020-10 ***Pre-Construction100%Evan Tenenbaumhttps://durhamnc.gov/3828/Downtown-Durham-Wayfinding-Project
  
Tenenbaum, Evan4.011/1/2019 2:11 PM

New Traffic Signal Installation

MLK Jr. Pkwy and Bay Point Drive and Broad Street and Murray Avenue
$150,000.00

In House Design Completed (McCain)

In House Design Underway (ASC/3)

2017-052017-012019-05 *** Date previoulsy adjusted *** (January 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination) - Cobmined with Broad and Murray2019-10 *** Dates previously adjusted from 2018-07 ***2020-4Pre-Construction90%Peter Nicholas
  
Nicholas, Peter3.010/7/2019 2:28 PM
New Traffic Signal Installation


Mangum St and Dillard St.
$175,000.00

Signal Construction is  completed  - Signal is in 30 Day Observation  Period..

2017-052018-012018-09 *** Date previoulsy adjusted *** (January 2018 Delayed by Ornamental Metal Pole Delivery 6 Months and to be managed by NCDOT) - City Staff Constructing Corridor Improvements along Mangum at Jackie Robinson and Morehead to complement project.2019-8 *** Dates previously adjusted from 2018-14 ***2019-10 *** Dates previously adjusted from 2019-06 ***Complete100%Peter Nicholas
  
Nicholas, Peter4.011/4/2019 2:34 PM

Durham Signal System Upgrade

Upgrade 38 City owned traffic signals (not-eligible for federal funding under U-5968)
$600,000.00

Signal equipment ordered

Designs for pending improvements underway

Utility Adjustments are underway

Ongoing2019-122019-07  *** Date previoulsy adjusted *** (January 2018 Delayed byNCDOT Signal System Compatibility/Specification Coordination)2018-072022-01 (The project timeline must align with the fiber installation for the NCDOT Signal SystemConstruction15%Peter Nicholas
  
Nicholas, Peter3.010/7/2019 2:29 PM
ST-286

Petition Streets Phase II: Pave Gravel Roads

Leonard Dr/Turner St; Lang St; Chalmers St; Amber Pl; Brunson St; Omah (Carver St to 3010 Omah)
$1,255,590.00

PW: The project manual is being prepared.  

RE:
AMBER PLACE: All properties acquired and closed.
BRUNSON DRIVE: Project plat has now been recorded. Closings have occurred on 3 of the 8 properties to acquire. The remaining properties are all owned by one party, closing anticiapted by 11/30.
CHALMERS STREET: All properties acquired and closed.
LANG STREET: All properties acquired and closed..
LEONARD/TURNER STREET: 25 properties to acquire. RE has Options from all property owners. Closings in process.
OMAH STREET: 12 properties to acquire. RE has Options from all property owners. Closings in process.

July 2018May 2019Dec 2019May 2020Aug 2021Design/ROW85Ed Venable
  
Fleischer, David5.011/4/2019 2:33 PM
ST-288a

​Bridge Repair Design

Various Locations

​PW: Initiated Task Order 4 for the inspection of the pedestrian bridges along the American Tobacco Trail. 


NANAMar 2018Aug 2018Aug 2019Design/ROW60Ed Venable
  
Venable, Ed3.011/4/2019 1:15 PM
ST-288b

​Bridge Asset Management Plan

Various Locations
$175,000.00

​PW:  The work on Phase Three is underway, an in depth review of the NCDOT bridge inspection reports.

NANAMay 2018Oct 2018Sept 2019Construction15Ed Venable
  
Venable, Ed3.011/4/2019 1:16 PM
New Traffic Signal Installation


US 15-501 Business at Hope Valley Road
$150,000.00

In House Design Underway - Awaiting construciton of curb ramps to complete design. US 15-501 and James Street (pedestrian crossing) will be added to this installation. 

2019-06 *** Date previoulsy adjusted *** (July 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination)2019-06 *** Date previoulsy adjusted *** (July 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination and Adding James Street Pedestrian Crossing to Scope)2019-06 *** Date previoulsy adjusted *** (January 2019 Delayed by NCDOT Signal System Compatibility/Specification Coordination and Adding James Street Pedestrian Crossing to Scope)2019-12 *** Dates previously adjusted from 2018-07 ***2020-04Pre-Construction90%Peter Nicholas
  
Nicholas, Peter2.010/7/2019 2:28 PM

2020 FY Speed Humps

Kirkwood Drive
$25,000.00

A total of 5 speed humps were added to Kirkwood Drive between Stadium Drive and Guess Road in Durham. 

Work is completed.

8/20198/29/201910/7/201910/31/2019Complete100Jessica Kemp
  
Nicholas, Peter6.011/4/2019 2:34 PM
2019 FY Curb Ramps
*COMPLETE*
Various Locations
$260,000.00

Contractor completed improvements at 22 locations throughout the City over a 6 month period. Road striping and solar-powered pedestrian crosswalk signs were coordinated at select locations by the Transportation Dept once GC completed construction.

2018-082018-082018-092019-032019-09Complete100Jessica Kemp
  
Kemp, Jessica3.010/29/2019 8:04 AM
ST-290

Street Repairs and Repaving 2019

Various Locations
$6,500,000.00

​PW: The paving is underway.

NANAFeb 2019May 2019Nov 2019Construction60Clint Blackburn
  
Venable, Ed3.011/4/2019 1:22 PM
ST-298

​Pavement Preservation 2019

Various Locations
$3,000,000.00

​PW: The paving is underway.

NANAMar 2019June 2019May 2020Construction60Clint Blackburn
  
Venable, Ed3.011/4/2019 1:24 PM
ST-299

​Asphalt Rejuvenation 2019

Various Locations
$150,000.00

​PW: The paving is complete. This project invloved the application of Reclamite.

NANAMar 2019June 2019May 2020Construction100Clint Blackburn
  
Venable, Ed3.011/4/2019 1:25 PM

***NEW***             

Pavement Marking Improvements - On Call

Various Locaitons
$150,000.00

Project Manual Prepared for Advertisement

2020-12N/A2019-102019-122020-12Pre-Construction95%Pete Nicholas
  
Nicholas, Peter3.011/4/2019 2:38 PM

​****NEW****

2020 Curb Ramps

Various Locations
$247,500.00

​Transportation is working up a project estimate and list of curb ramp improvement locations. General Services will request a 14 day advertisement period once project manual details are provided.

11/30/2019n/a12/15/20191/15/20206/30/2020Design/ROW25Jessica Kemp
  
Nicholas, Peter7.011/4/2019 2:37 PM

​Paving

Various Locations
$7,000,000.00

​The Bid Opening will occured October 25. Paving will occur in spring 2020.

NANAOct 2019April 2020Nov 2020Pre-Construction50Clint Blackburn
  
Venable, Ed1.011/4/2019 1:28 PM

​Pavement Preservation

Various Locations
$1,000,000.00
NANAOct 2019April 2020Nov 2020Pre-Construction50Clint Blackburn
  
Venable, Ed1.011/4/2019 1:30 PM

​****NEW****

2020 Directional Boring Utility Work

Various Locations
$65,000.00


Project Manual Prepared for Advertisement
11/30/2019N/A12/31/20191/30/20206/30/2020Design/ROW25Pete Nicholas
  
Nicholas, Peter5.011/4/2019 2:40 PM

​****NEW****

2020 Inductive Loops


Various Locations
$25,000.00


Bid Awarded to Fulcher Electric of Fayetteville
10/01/2020N/A10/01/201912/01/20196/30/2021Pre-Construction50Pete Nicholas
  
Nicholas, Peter1.011/4/2019 2:45 PM