CodiNetX

Skip Navigation LinksLocally Managed Road Projects

  
Project Description
  
  
Monthly Updates
  
  
  
  
  
  
  
  
  
  
Sum= $37,486,940.00
ST-257

Road Extension

​Carver Street
$7,268,500.00

PW: The estimated completion date and opening of the Carver Street Extension to traffic is the first week in September  The ROW annexation was approved at the August 5, 2019 City Council meeting.

Nov 2013Mar 2015Sept 2015Sept 2016Sept 2019Construction95Ed Venable
  
ST-264

Road Widening

​Fayetteville Rd: Barbee to Riddle
$12,260,000.00
PW: The work continues for debris removal, signal work, hauling in borrow, grading and storm drainage installation.

RE: All properties (37 in total) are now owned by the City. RE and CAO will work together on mediation/settlement of condemnation suits filed.
March 2016Dec 31, 2018 *** Dates previously adjusted *** (July 2018  Delayed by need to condemn and Duke Energy negotiations) (Jan 2018 Delayed by Duke Energy negotiations)July 2018 *** Dates previously adjusted *** (Feb 2018 Delayed by Duke Energy negotiations)Feb 2019 *** Dates previously adjusted *** (Oct 2018 Readvertisement requried) (July 2018 Delayed by Duke Energy negotiations)Oct 2020 *** Dates previously adjusted *** (April 2020 Readvertisement requred) (Jan 2020 Delayed by Duke Energy negotiations)Construction4Ed Venable
  
ST-271

Petition Street 2017

Ardmore Dr, Castell Dr, Missell Ave, Windburn Ave,
PW: Construction has begun on Missell Ave and Ardmore Dr. The remainign streets are Castell Dr and Winburn Ave.

May 20175/23/2018Sept 2018May 20192020-03Construction7Clint Blackburn
  
U-5823

Road Extension

Woodcroft Parkway Extension:  Hope Valley Rd. to Garrett Rd.
$4,217,100.00

Contract negotiation and execution has been delayed due to staff vacancies.  Manday Hours/Rates estimates were returned for corrections and have been re-sent to NCDOT for review.  

2020-122021-052021-082022-032025-08Planning80 %Ellen Beckmann
  
C-5605H

Downtown Durham ​Wayfinding Program

Various Locations within Downtown Durham
$695,750.00

Draft Submisssion sent to NCDOT  in mid-July and approved in August. Major COA and Minor COA have been approved. ROW also submitted and approved. CE has been submtitted to SHPO and soon to NCDOT. Currently doing final fixes internally and waiting on word back from NCDOT for corrections. 

2019-09 *** Dates previously adjusted from 2019-07*** 2019-10 *** Dates previously adjusted from 2019-08 ***2019-12 *** Dates previously adjusted from 2019-10***2020-01 *** Dates previously adjusted from 2019-11 ***2020-12 *** Dates previously adjusted from 2020-10 ***Design/ROW70%Evan Tenenbaumhttps://durhamnc.gov/3828/Downtown-Durham-Wayfinding-Project
  

New Traffic Signal Installation

MLK Jr. Pkwy and Bay Point Drive and Broad Street and Murray Avenue
$150,000.00

In House Design Completed (McCain)

In House Design Underway (ASC/3)

2017-052017-012019-05 *** Date previoulsy adjusted *** (January 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination) - Cobmined with Broad and Murray2019-09 *** Dates previously adjusted from 2018-07 ***2020-4Pre-Construction99%Peter Nicholas
  
New Traffic Signal Installation


Mangum St and Dillard St.
$175,000.00

Awaiting Delivery of Signal Supports - *** UPDATE - Signal Supports will be poured in June 2019 (Per contractor)***

2017-052018-012018-09 *** Date previoulsy adjusted *** (January 2018 Delayed by Ornamental Metal Pole Delivery 6 Months and to be managed by NCDOT) - City Staff Constructing Corridor Improvements along Mangum at Jackie Robinson and Morehead to complement project.2019-06 *** Dates previously adjusted from 2018-14 ***2019-09 *** Dates previously adjusted from 2019-06 ***Construction10%Peter Nicholas
  

Durham Signal System Upgrade

Upgrade 38 City owned traffic signals (not-eligible for federal funding under U-5968)
$600,000.00

Signal equipment ordered

Designs for pending improvements underway

Ongoing2019-122019-07  *** Date previoulsy adjusted *** (January 2018 Delayed byNCDOT Signal System Compatibility/Specification Coordination)2018-072022-01 (The project timeline must align with the fiber installation for the NCDOT Signal SystemConstruction15%Peter Nicholas
  
ST-286

Petition Streets Phase II: Pave Gravel Roads

Leonard Dr/Turner St; Lang St; Chalmers St; Amber Pl; Brunson St; Omah (Carver St to 3010 Omah)
$1,255,590.00

PW: This project is in acquisitions.  

RE:
AMBER PLACE: 7 properties to acquire. All acquisitions are complete. Closings have all occurred without use of plat as PW does not yet have plat completed.
BRUNSON DRIVE: 8 properties to acquire. PW has recently re-designed the project and RE now has Options from all property owners. Closings are delayed until PW produces plats for recordation.
CHALMERS STREET: 15 properties to acquire. All acquisitions are complete.
LANG STREET: 16 properties to acquire. All acquisitions are complete.
LEONARD/TURNER STREET: 25 properties to acquire. RE now has Options from all property owners. Closings in process..
OMAH STREET: 12 properties to acquire. All acquisitions are complete.

July 2018May 2019Dec 2019May 2020Aug 2021Design/ROW85Thomas Wilcoxson
  
ST-288a

​Bridge Repair Design

Various Locations

​PW: Task Order Two is underway to design the selected bridge repairs. Task Order Three is just beginning to look at the second round of bridges identified as needing repairs by the most recently received NDCDOT reports.


NANAMar 2018Aug 2018Aug 2019Design/ROW55Ed Venable
  
ST-288b

​Bridge Asset Management Plan

Various Locations
$175,000.00

​PW:  The consultant met with PW staff to review Task Two, how PW does business. The work on Phase Three is underway, an in depth review of the NCDOT bridge inspection reports.

NANAMay 2018Oct 2018Sept 2019Construction10Ed Venable
  
New Traffic Signal Installation


US 15-501 Business at Hope Valley Road
$150,000.00

In House Design Underway - Awaiting construciton of curb ramps to complete design. US 15-501 and James Street (pedestrian crossing) will be added to this installation. 

2019-06 *** Date previoulsy adjusted *** (July 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination)2019-06 *** Date previoulsy adjusted *** (July 2018 Delayed by NCDOT Signal System Compatibility/Specification Coordination and Adding James Street Pedestrian Crossing to Scope)2019-06 *** Date previoulsy adjusted *** (January 2019 Delayed by NCDOT Signal System Compatibility/Specification Coordination and Adding James Street Pedestrian Crossing to Scope)2019-12 *** Dates previously adjusted from 2018-07 ***2020-03Pre-Construction25%Peter Nicholas
  

***NEW***

2020 FY Speed Humps

Kirkwood Drive
$30,000.00

A total of 5 speed humps will be added to Kirkwood Drive between Stadium Drive and Guess Road in Durham.

8/20198/28/201910/1/201910/31/2019Design/ROW100%Jessica Kemp
  
2019 FY Curb Ramps
Various
$260,000.00

Project under construction. 

Contractor has completed 20 locations throughout the City since work began late March 2019. Road striping and solar-powered pedestrian crosswalk signs will be coordinated at select locations by the Transportation Dept once GC construction is complete. Ground plane art by Madiha Malik will be coordinated by GSD's Cultural and Public Art Program for the mid-block crossing installed on W Club Blvd at Northgate Mall. Completion Date: 9/30/19 (extended by Change Order) 

2018-082018-082018-092019-032019-09 *** Dates previously adjusted from 2019-6 ***Construction90Jessica Kemp
  
ST-290

Street Repairs and Repaving 2019

Various Locations
$6,500,000.00

​PW: The paving will begin August 21, 2019.

NANAFeb 2019May 2019Nov 2019Construction0Clint Blackburn
  
ST-298

​Pavement Preservation 2019

Various Locations
$3,000,000.00

​PW: The paving began August 19, 2019.

NANAMar 2019June 2019May 2020Construction0Clint Blackburn
  
ST-299

​Asphalt Rejuvenation 2019

Various Locations
$150,000.00

​PW: The paving began August 19, 2019.

NANAMar 2019June 2019May 2020Construction0Clint Blackburn
  

Aerial Utility Adjustments

Various Locations
$600,000.00

The bid opening is scheduled for May 20. ***UPDATE - First Advertisement did not secure 3 bids.  Will be readvertised in June 2019 with a July 2019 bid opening date.***

NANAJuly 2019August 2019August 2021Pre-Construction50