CodiNetX

Skip Navigation LinksBicycle/Pedestrian Projects

  
  
Project Description
  
  
Monthly Update
  
  
  
  
  
  
  
  
  
  
  
History
  
  
  
Sum= $48,299,591.00Sum= $12,898,714.00
EB-4707BN/A

Bike Lanes and Sidewalk; Roundabout at Pope Road

​​Old Durham/Old Chapel Hill Rd: Garrett Road to Pope Road
$7,499,897.00
May 5, 2019 Update:  The final layer of asphalt has been put down. NCDOT is currently installing thermoplastic pavement markings and expects that the project will be substanitally complete by the end of May.

City and DCHC MPO staff have received requests for lighting at the Pope Road roundabout; but that location is outside of the City of Durham limits and is also not in Chapel Hill's limits (NCDOT and the County typically do not provide streetlights on secondary roads, but NCDOT is reportedly reconsidering this policy).  Lighting of the Mt. Moriah Road roundabout, as well as lighting along the corridor up to Garrett Road, is being addressed by a lighting project ordered from Duke Energy by the Transportation Department.  City and NCDOT staff have also received requests that the roundabouts be landscaped, and it is our understanding that Council Member Reece is discussing this with appropriate staff in the General Services Department.
N/AN/A2017-052017-062019-05Construction89.63
$1,197,979.00
$5,999,918 federal  ($302,000 state)STP-DA (PE, ROW, CON); TAP-DA (ROW, CON)February 2008; Supplemental July 2017; Supplemental May 2019

​DCHC MPO Feasibility Study completed in February 2006

Dale McKeelClick hereClick Here for More Details
U-4726HOSW-44

Bike Lanes and Sidewalk

​Carpenter Fletcher Rd: Woodcroft Pkwy to Alston Ave
$4,688,983.00
PW: SEPI provided an acquisitions estimate from Carolina Land Acquisitions which was reviewed and resubmitted to SEPI for revision; a supplimental agreemtn will be needed for the acquisitions scope.





Dec 2019 (Dec 2018) May 2021 (June 2019)   July 2021 (March 2020)  Dec 2021 (Aug 2020)April 2023 (Dec 2021) Design/ROW83
$1,157,930.00
$3,531,053.00STP-DA (PE, ROW, CON)July 2015

​SEPI Engineering awarded the Design Contract.

David CatesClick hereClick Here for More Details
U-4724SW-45

Bike Lanes and Sidewalk

Cornwallis Rd: S. Roxboro St to Chapel Hill Rd
$5,432,020.00

 PW: Alta is preparign teh acquisitions scope and fees. Supplimental agreements are needed for road realignment design to avoid waterline distribution main and for acquisitions.


April 2019 (Nov 2018)June 2019 Mar 202Aug 2020Dec 2021 Design/ROW60
$1,214,867.00
$4,217,153.00STP-DA (PE, CON)June 2015

Alta Engineering was awarded the Design Contract.

Neil AllenClick hereClick Here for More Details
U-4726HNSW-46

Sidepath/Bike Lanes and Sidewalk

Hillandale Rd: I-85 to NC 147
$3,107,941.00

 PW: RKA provided scope and fees for acquisitions (Telics); a supplemental agreement will be needed for the acquisitions scope.

Jan 2020 (Nov 2018)June 2021 (May 2019) Aug 2021 (Feb 2020) Jan 2022 (July 2020) Mar 2023 (Sept 2021)Design/ROW85
$817,442.00
$2,290,499.00STP-DA (PE, ROW, CON)June 2015

Ramey Kemp was awarded the Design Contract.

 

David CatesClick hereClick Here for More Details
C-4928SW-47

Bike Lanes and Sidewalk

​Morreene Rd: Erwin Rd to Neal Rd
$6,317,129.00

 PW: Kimley Horn provided scope and fees for acquisitions (Telics), and a waterline design. Both documents were reviewed and resubmitted to Kimley Horn for revision. A supplemental agreement is required for both.

A supplimental agreement will also be needed to add funding from NCDOT for the required road resurfacing.

Jan 2020 (Nov 2018)May 2021 (June 2019) July 2021 (Feb 2020) Dec 2021 (July 2020) April 2023 (Nov 2021) Design/ROW75
$1,418,418.00
$4,898,711.00STP-DA (PE, ROW, CON); CMAQ (CON)June 2015

​Kimley Horn was awarded the Design Contract.

 

David CatesClick hereClick Here for More Details
C-5183BSW-40

Sidewalk

​Alston Ave: Capps Street to Riddle Road
$913,339.00

PW: The project is in acquisitions.

RE: Real estate activity is complete. Right of Way Certification received from NCDOT on 5/2.

2017-082018-102019-07 *** Dates previously adjusted*** (June 2019 Design delays)2020-01 *** Dates previously adjusted*** (Dec 2019 Design delays)2020-09 *** Dates previously adjusted*** (Aug 2020 Design delays)Design/ROW100
$268,979.00
$644,360.00CMAQ (CON); *AMENDMENT TO ADD ROWOctober 2016
Mr. Kitty ThomasClick hereClick Here for More Details
EB-5514SW-39

Bike Lanes (Hope Valley to Cornwallis) and Sidewalk

University Dr: Chapel Hill Rd to Cornwallis Rd
$1,586,063.00

PW: Construction is underway.

April 2015Dec 2017 ***Dates previously adjusted*** (Sept 2017 - Determining how to Condemn for Duke Energy)Oct 2018 ***Dates previously adjusted*** (July 2018 Determining how to Condemn for Duke Energy)Mar 2019 ***Dates previously adjusted*** (Dec 2018 Determining how to Condemn for Duke Energy)Jan 2020 ***Dates previously adjusted*** (July 2019 Determining how to Condemn for Duke Energy)Construction20
$561,063.00
$820,000 federal ($205,000 state)STP-EB (CON)December 2014
Neil AllenClick hereClick Here for More Details
EB-5703SW-52

Sidewalk (both sides Kangaroo to Hillsborough, one side Hillsborough to Sprunt)

 

LaSalle St: Kangaroo Dr to Sprunt Ave
$742,232.00
PW: NCDOT has approved revised 25% plans and 1st CE version. Consultant submitted initial request to Northfolk Southern Railroad regarding reviewing design and preparing a Preliminary Engineering estimate.
Jan 2020 (Mar 2019) Dec 2021 (Sept 2019) Feb 2022 (June 2020)  July 2022 (Nov 2020) Sept 2023 (Jan 2022)  Design/ROW54
$204,552.00
$537,680.00TAP (PE, CON)August 2016

​Sepi was awarded the Design Contract.

David CatesClick hereClick Here for More Details
EB-5704SW-53

Sidewalk (one side)

Raynor St: N Miami Blvd to Hardee St
$364,435.00
PW: Legal descriptions are being prepared. 

June 2019 (Jan 2019) Feb 2021 (July 2019) April 2021 (April 2020) Sept 2021 (Sept 2020) Aug 2022 (Aug 2021) Design/ROW90
$100,435.00
$264,000.00TAP (PE, CON)August 2016

​Ramey-Kemp was awarded the Design Contract.

Neil AllenClick hereClick Here for More Details
EB-5715SW-50

Sidewalk (east side)

North Duke St: Murray Ave to Roxboro Rd
$1,608,372.00

PW: The second public meeting was held with approximately 10 attending.

Oct 2019 (Feb 2019)Sept 2021 (Oct 2019)  Nov 2021 (July 2020)  April 2022 (Dec 2020)  June 2023 (Feb 2022)Design/ROW70
$443,252.00
$1,165,120.00TAP (PE, CON)August 2016

Kimley-Horn was awarded the Design Contract. 

Neil AllenClick hereClick Here for More Details
EB-5708SW-51

Sidewalk (south side)

NC 54: NC 55 to City Limits
$364,435.00

PW: NCDOT has approved 65% plans. NCDOT approved the CE document. The scope and fee for the retaining wall design is being reviewed; a supplemental agreement will be required. 

Feb 2020 (Jan 2019) Jan 2022 (July 2019) Mar 2022 (April 2020) Aug 2022 (Sept 2020) July 2023 (Aug 2021)Design/ROW76
$34,435.00
$330,000.00SRTS (PE, CON)August 2016

Davenport ​was awarded the Design Contract.

David CatesClick hereClick Here for More Details
N/ASW-41

Sidewalk

N Roxboro Rd: Pacific Ave to Murray Ave
$445,000.00

PW: The project is in acquisition.

RE: 31 properties to acquire. 26 owners have provided Options to Purchase to the City. Closings with owners will commence, although PW has indicated that a plat cannot be prepared for recordation until ~8/2019. 

Aug 2017February, 2019Dec 2018  *** Dates previously adjusted *** (date adjusted due to Real Estate staff availability (Sept 2018)May 2019  *** Dates previously adjusted *** (date adjusted due to Real Estate staff availability (Feb 2019) (Dec 2019 erroneous entry)April 2020  *** Dates previously adjusted *** (date adjusted due to Real Estate staff availability (Jan 2020) (Aug 2020 erroneous entry)Design/ROW80
$445,000.00
N/AN/AN/A
Mr. Kitty ThomasClick Here for More Details
N/ASW-62

2018 Sidewalk Repair

Various locations
$1,539,549.00
PW: The project is complete.
NANANov 20172018-04May 2019Construction100
N/AN/AN/A
Mr. Kitty ThomasClick Here for More Details
N/ABike+Walk Phase I

Sidewalk      B+W I       SW-66

Clayton and Freeman Road
$203,000.00

​PW: In review & permitting process

May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$203,000.00
N/AN/AN/A
Tim WatsonClick hereClick Here for More Details
N/ABike+Walk Phase I
Sidewalk      B+W I       SW-66
Hillsborough Road: LaSalle to Neal/Bus Stop
$380,000.00

PW: In review & permitting process

May 2019 (was Jan 2019)July 2019March 20202020-08December 2021Design85
$380,000.00
N/AN/AN/A
Jeanie JamesClick hereClick Here for More Details
N/ABike+Walk Phase I
Sidewalk      B+W I       SW-66
Holloway Street: Gary to Guthrie
$487,500.00

PW: In review & permitting process

May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$487,500.00
N/AN/AN/A
Kyle PhinneyClick hereClick Here for More Details
N/ABike+Walk Phase I
Sidewalk      B+W I       SW-66
Old Oxford Road: Dearborn to Roxboro
$206,250.00

PW: In review & permitting process
May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$206,250.00
N/AN/AN/A
Tim WatsonClick hereClick Here for More Details
N/ABike+Walk Phase I
Sidewalk      B+W I       SW-66
Corporation St: North Duke St to Mangum
$310,000.00

PW: In review & permitting process
May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$310,000.00
N/AN/AN/A
Kevin ZelayaClick hereClick Here for More Details
C-5605EBicycle Lane Striping

Bike Lanes

8 Miles
$829,170.00
Consultant is preparing final design package for NCDOT review.  Signal plans are underway.  CE document has been approved.  Municipal agreement has been fully executed.





May 2019 (December date adjusted due to staff vacancies)N/ASeptember 2019 (April date adjusted due to staff vacancies)February 2020 (September date adjusted due to staff vacancies)May 2020 (December date adjusted due to staff vacancies)Design95
$165,834.00
663,336.00CMAQTBD
Ellen Beckmannhttp://durhamnc.gov/3606/2018-Bicycle-ImprovementsClick Here for More Details
C-5605IDurham Neighborhood Bike Route

Bike Lane/Bike Boulevard

7 Miles
$631,873.00

Public Meeting held December 11th on proposed routes and concept designs. More detailed engineering and categorical exclusion work underway.

Door hangers placed at all properties on proposed routes in early February.  Postcard mailed to all property owners of record in early February.  Residents requested to contact city staff with questions or comments and fill out an on-line feedback form.

As of March 4, 2019, city staff have been contacted by a handful or residents and more than 100 have completed the on-line feedback form.

The Environmental Document (CE) and Right-of-Way Plans Complete (RPC) are scheduled to be completed by 3/29/19.
July 2019 (October 2018 date adjusted due to NCDOT review times)N/ASeptember 2019 (January 2019 adjusted due to delay in design phase)November 2019 (May 2019 date adjusted due to delay in design phase)April 2020 (October 2019 date adjusted due to delay in design phase)Design50
$126,375.00
$505,498.00CMAQOctober 10, 2017
Dale McKeelhttp://durhamnc.gov/3763/Neighborhood-Bike-RoutesClick Here for More Details
EB-5834SW-72

Sidewalks (both sides)

Guess Road: Hillcrest Drive to West Carver Street
$1,103,803.00

PW: The project manual is being developed.  

January 2020August 2021October 2021May 2022December 2022Planning95
$375,803.00
728,000.00Transportation Alternatives Program (TAP)
Thomas WilcoxsonClick Here for More Details
SW-70

Bike+Walk Sidewalk 2019

Cooper, Morehead, University, Lakewood, Carlton, Queen, Lawson, Hilllandale, Seminary, Murray, Sima
$400,000.00
PW: White Oak is preparing a work schedule and submittals in advance of beginning the work.
NANA2018-122018-042020-02Pre-Construction75
Mr. Kitty ThomasClick Here for More Details
NASW-67

​Sidewalk Repair 2019

Various locations
$1,420,000.00

​PW: A pre-bid meeting was held on May 9, 2019.

NANAFebruary 2019May 2019March 2020Pre-Construction75
NANANA
Kitty ThomasClick Here for More Details
N/ABike+Walk Phase II SW-68

Sidewalk       B+W II     SW-68


Southwest Durham Drive- 3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.
June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

Jeanie JamesClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk        B+W II     SW-68

Fulton Street-Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

Kyle PhinneyClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk      B+W II     SW-68

Broad Street-Installing sidewalk between Hillcrest Drive and Forest Road.
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Installing sidewalk between Hillcrest Drive and Forest Road.

Kyle PhinneyClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk      B+W II     SW-68

Holt School- In front of Holt School and north to Valley Drive.
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Kevin ZelayaClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk      B+W II     SW-68

North Pointe-Connect existing sidewalk between McDonalds and Red Roof Inn.
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Tim WatsonClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk      B+W II     SW-68

Fayetteville-From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

Kyle PhinneyClick Here for More Details
N/ABike+Walk Phase II

​Sidewalk      B+W II     SW-68

Stadium Drive-From Olympic to Duke Street
June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From Olympic to Duke Street

Kevin ZelayaClick Here for More Details
1 - 30Next