Project Description
  
  
  
Monthly Update
  
  
  
  
  
  
  
  
  
  
  
History
  
  
  
  
  
Sum= $60,066,536.00Sum= $18,145,753.00
1
EB-4707BN/A

Bike Lanes and Sidewalk; Roundabout at Pope Road

Dale McKeel​​Old Durham/Old Chapel Hill Rd: Garrett Road to Pope Road
$7,499,897.00
 
Project is complete

City and DCHC MPO staff have received requests for lighting at the Pope Road roundabout; but that location is outside of the City of Durham limits and is also not in Chapel Hill's limits (NCDOT and the County typically do not provide streetlights on secondary roads, but NCDOT is reportedly reconsidering this policy).  Lighting of the Mt. Moriah Road roundabout, as well as lighting along the corridor up to Garrett Road, is being addressed by a lighting project ordered from Duke Energy by the Transportation Department.  City and NCDOT staff have also received requests that the roundabouts be landscaped, and it is our understanding that Council Member Reece is discussing this with appropriate staff in the General Services Department.
N/AN/AMay 2017June 2017June 2019Construction100
$1,197,979.00
$5,999,918 federal  ($302,000 state)STP-DA (PE, ROW, CON); TAP-DA (ROW, CON)February 2008; Supplemental July 2017; Supplemental May 2019

​DCHC MPO Feasibility Study completed in February 2006

Click hereClick Here for More DetailsTaylor, Brian4.02/3/2020 9:59 AM
2
U-4726HOSW-44

Bike Lanes and Sidewalk

David Cates​Carpenter Fletcher Rd: Woodcroft Pkwy to Alston Ave
$4,688,983.00
PW: Plans are at 90%. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 
2019-12 May 2021 July 2021 Dec 2021 April 2023 Design/ROW90
$1,157,930.00
$3,531,053.00STP-DA (PE, ROW, CON)July 2015

​SEPI Engineering awarded the Design Contract.

Click hereClick Here for More DetailsVenable, Ed9.07/6/2020 2:04 PM
3
U-4724SW-45

Bike Lanes and Sidewalk

Neil AllenCornwallis Rd: S. Roxboro St to Chapel Hill Rd
$5,432,020.00

PW: Plans are at 65%. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

April 2020November 2020October 2021Mar 2022July 2023Design/ROW65
$1,214,867.00
$4,217,153.00STP-DA (PE, CON)June 2015

Alta Engineering was awarded the Design Contract.

Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:04 PM
4
U-4726HNSW-46

Sidepath/Bike Lanes and Sidewalk

David CatesHillandale Rd: I-85 to NC 147
$3,107,941.00

PW: Plans are at 100% and under NCDOT review. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

Jan 2020 June 2021Aug 2021 Jan 2022 Mar 2023 Design/ROW95
$817,442.00
$2,290,499.00STP-DA (PE, ROW, CON)June 2015

Ramey Kemp was awarded the Design Contract.

 

Click hereClick Here for More DetailsVenable, Ed9.07/6/2020 2:08 PM
5
C-4928SW-47

Bike Lanes and Sidewalk

David Cates​Morreene Rd: Erwin Rd to Neal Rd
$6,317,129.00

PW: Plans are at 100% and being reviewed by NCDOT. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

Jan 2020 May 2021July 2021Dec 2021 April 2023 Design/ROW99
$1,418,418.00
$4,898,711.00STP-DA (PE, ROW, CON); CMAQ (CON)June 2015

​Kimley Horn was awarded the Design Contract.

 

Click hereClick Here for More DetailsVenable, Ed7.07/6/2020 2:09 PM
6
C-5183BSW-40

Sidewalk

Mr. Kitty Thomas​Alston Ave: Capps Street to Riddle Road
$913,339.00

PW: Plans are at 100% and under review by NCDOT. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

2017-082018-102019-11 2021-05 2021-04 Pre-Construction95
$268,979.00
$644,360.00CMAQ (CON); *AMENDMENT TO ADD ROWOctober 2016
Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:00 PM
7
EB-5514SW-39

Bike Lanes (Hope Valley to Cornwallis) and Sidewalk

Neil AllenUniversity Dr: Chapel Hill Rd to Cornwallis Rd
$1,586,063.00

PW: Construction has resumed following the Mayor's Shut Down Order.

2015-04Dec 2017Oct 2018 Mar 2019 Jan 2020Construction75
$561,063.00
$820,000 federal ($205,000 state)STP-EB (CON)December 2014
Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:03 PM
8
EB-5703SW-52

Sidewalk (both sides Kangaroo to Hillsborough, one side Hillsborough to Sprunt)

 

David CatesLaSalle St: Kangaroo Dr to Sprunt Ave
$742,232.00
PW: Plans are at 90%. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 
Jan 2020Dec 2021Feb 2022July 2022Sept 2023Design90
$204,552.00
$537,680.00TAP (PE, CON)August 2016

​Sepi was awarded the Design Contract.

Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:09 PM
9
EB-5704SW-53

Sidewalk (one side)

Neil AllenRaynor St: N Miami Blvd to Hardee St
$364,435.00
PW: Plans are complete. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 
June 2019Feb 2021April 2021Sept 2021Aug 2022Design/ROW99
$100,435.00
$264,000.00TAP (PE, CON)August 2016

​Ramey-Kemp was awarded the Design Contract.

Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:10 PM
10
EB-5715SW-50

Sidewalk (east side)

Neil AllenNorth Duke St: Murray Ave to Roxboro Rd
$1,608,372.00

PW: Plans are at 100% and being reviewed by the City for final signature. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

Oct 2019Sept 2021Nov 2021April 2022June 2023Design/ROW95
$443,252.00
$1,165,120.00TAP (PE, CON)August 2016

Kimley-Horn was awarded the Design Contract. 

Click hereClick Here for More DetailsVenable, Ed8.07/6/2020 2:11 PM
11
EB-5708SW-51

Sidewalk (south side)

David CatesNC 54: NC 55 to City Limits
$364,435.00

PW: Plans are at 90%. Following revelations of budget shortfalls, we are awaiting a decision by NCDOT to allow the City to move forward with the project. 

2020-02 Jan 2022 Mar 2022Aug 2022July 2023Design/ROW90
$34,435.00
$330,000.00SRTS (PE, CON)August 2016

Davenport ​was awarded the Design Contract.

Click hereClick Here for More DetailsVenable, Ed7.07/6/2020 2:11 PM
12
N/ASW-41

Sidewalk

Mr. Kitty ThomasN Roxboro Rd: Pacific Ave to Murray Ave
$445,000.00

PW: The project will be advertised in August.

RE: All property optioned, closings in progress; two remaining to close. PW may move forward with construction.

Aug 2017Dec 2019Aug 2020Jan 2021 Dec 2021Design/ROW95
$445,000.00
N/AN/AN/A
Click Here for More DetailsFleischer, David11.07/6/2020 2:44 PM
18
C-5605EBicycle Lane Striping

Bike Lanes

Ellen Beckmann8 Miles
$1,252,713.00
NCDOT construction authorization was approved in September 2019.  Consultant needs to prepare updated final PS&E package with pavement marking and signal plans.





May 2019 (December date adjusted due to staff vacancies)N/ASeptember 2019 (April date adjusted due to staff vacancies)February 2020 (September date adjusted due to staff vacancies)May 2020 (December date adjusted due to staff vacancies)Design99
$250,543.00
1002170CMAQ2/18/2019
http://durhamnc.gov/3606/2018-Bicycle-ImprovementsClick Here for More DetailsBeckmann, Ellen2.011/4/2019 2:45 PM
19
C-5605IDurham Neighborhood Bike Route

Bike Lane/Bike Boulevard

Dale McKeel7 Miles
$631,873.00

Public Meeting held December 11th on proposed routes and concept designs. More detailed engineering and categorical exclusion work underway.

Door hangers placed at all properties on proposed routes in early February.  Postcard mailed to all property owners of record in early February.  Residents requested to contact city staff with questions or comments and fill out an on-line feedback form.

As of March 4, 2019, city staff have been contacted by a handful or residents and more than 100 have completed the on-line feedback form.

The Environmental Document (CE) and Right-of-Way Plans Complete (RPC) are scheduled to be completed by 3/29/19.
July 2019 (October 2018 date adjusted due to NCDOT review times)N/ASeptember 2019 (January 2019 adjusted due to delay in design phase)November 2019 (May 2019 date adjusted due to delay in design phase)April 2020 (October 2019 date adjusted due to delay in design phase)Design50
$126,375.00
$505,498.00CMAQOctober 10, 2017
http://durhamnc.gov/3763/Neighborhood-Bike-RoutesClick Here for More DetailsTaylor, Brian1.08/29/2019 2:23 PM
20
EB-5834SW-72

Sidewalks (both sides)

TransportationGuess Road: Hillcrest Drive to West Carver Street
$1,103,803.00

Project is on hold

$375,803.00
728,000.00Transportation Alternatives Program (TAP)
Click Here for More DetailsBeckmann, Ellen2.011/4/2019 2:46 PM
22
NASW-67

​Sidewalk Repair 2019

Kitty ThomasVarious locations
$1,420,000.00

​PW: Construction is underway. 

NANAApril 2019Nov 2019November 2020Construction40
NANANA
Click Here for More DetailsVenable, Ed7.07/6/2020 1:58 PM
23
N/ASW-68

Sidewalk B+W II


Jeanie JamesSouthwest Durham Drive- 3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020.  

November 6, 2019 NCDOT is non-responsive on request for information.  This is holding up the BWII final submittal.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

Click Here for More DetailsLecky, Jeff9.02/3/2020 1:42 PM
24
N/ASW-68

Sidewalk B+W II


Kyle PhinneyFulton Street-Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.


August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

Click Here for More DetailsLecky, Jeff5.02/3/2020 1:38 PM
25
N/ASW-68

Sidewalk B+W II


Kyle PhinneyBroad Street-Installing sidewalk between Hillcrest Drive and Forest Road.

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Installing sidewalk between Hillcrest Drive and Forest Road.

Click Here for More DetailsLecky, Jeff5.02/3/2020 1:38 PM
26
N/ASW-68

Sidewalk B+W II


Kevin ZelayaHolt School- In front of Holt School and north to Valley Drive.

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Click Here for More DetailsLecky, Jeff4.02/3/2020 1:38 PM
27
N/ASW-68

Sidewalk B+W II


Tim WatsonNorth Pointe-Connect existing sidewalk between McDonalds and Red Roof Inn.

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Click Here for More DetailsLecky, Jeff4.02/3/2020 1:38 PM
28
N/ASW-68

Sidewalk B+W II


Kyle PhinneyFayetteville-From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

Click Here for More DetailsLecky, Jeff4.02/3/2020 1:38 PM
29
N/ASW-68

Sidewalk B+W II


Kevin ZelayaStadium Drive-From Olympic to Duke Street

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From Olympic to Duke Street

Click Here for More DetailsLecky, Jeff5.02/3/2020 1:38 PM
30
N/ASW-68

Sidewalk B+W II


Jeanie JamesRaynor Steet - ​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

November 20, 2019 PW Design met with Duke Energy about pole relocations.  Said it could take another 7-8 months per new URA just signed to approve design.  Based on this the delivery of plans and permits is pushed back from June 2020 to November 2020. 

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

Dec 1 2020 Was-June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

Click Here for More DetailsLecky, Jeff4.02/3/2020 1:38 PM
31

2020 Signalized Pedestrian Improvements

1. Arnette Avenue and Morehead Avenue 2. Driver Street and East Main Street 3. East Lawson Street and Lincoln Street 4. East Lawson Street and Merrick Street 5. East Main Street and Dillard Street 6. West Markham Avenue and Washington Street
$450,000.00

Project Currently Advertised (Bid Opening July 21).

Actual Design Completion September 2019N/AJuly 2020April 2019(Design); December 2020 (Construction); Project Readvertised with reopening for July 2020.  Construction completion expected by end of calendar year.December 2020 (Changed from April 2020)Bid90%
Click Here for More DetailsNicholas, Peter22.07/6/2020 2:24 PM
32

HUD Pedestrian Upgrades

***PROJECT COMPLETED***

C-0166 Lawson St. at Ridgeway Ave. C-0063 Bacon St. at Pettigrew St. 05-1967 SR 1118 (Fayetteville St.) at Cecil St.   05-0333 NC 98 at Adams St. 05-1032 NC 55 (Avondale Dr.) at Trinity Ave. 05-1031 NC 55 (Avondale Dr.) at Markham Ave.  05-0271 US 70 Bus.
$600,000.00

PROJECT COMPLETED
June 2020June 2019July 2019April 2019(Design); March - Changed from December 2020 (Construction); Construction 33% complete)June 2020Construction100%
Click Here for More DetailsNicholas, Peter10.07/6/2020 2:24 PM
33
EB-5720

R. Kelly Bryant Bridge Trail


John Paces-WilesNC55 at Dakota Street to Drew Granby Park
$5,414,031.00

​​This bicycle and pedestrian trail will be approximately 3 miles long. It will connect the existing Rocky Creek Trail on Dakota Street north to the Drew/Granby Park located on Drew Street in Durham. The trail will connect users to an existing trail network, surrounding neighborhoods, NC Highway 55, Burton Park, Burton Elementary School, the 147 blue pedestrian bridge, Eastway Elementary School, East End Park, Long Meadow Park, and Drew/Granby Park.

Preliminary design is underway. The 30% design submittal is expected in early September. Staff anticipates taking a design amendment to City Council for approval for additional work associated with the final trail alignment not included in the original scope.

Staff will determine if additional federal funds are needed at 65% design.

Jan 2023April 2023Aug 2024Design32
$1,424,410.00
$3,989,621Transportation Alternative ProgramSeptember 2017, April 2018
Project WebsiteClick Here for More DetailsPaces-Wiles, John16.07/31/2020 3:58 PM
34

​Sidewalk (west side), cross walks and bus stop amenities

John Paces-WilesChapel Hill Rd: Morehead Ave to W. Lakewood Ave.
$590,000.00

PM: 90% design submittal was received on June 1, 2020. Property acquisitions to run into January, and project to bid in March 2021. 

RE: Real Estate and PM meeting with surveyor on 8/5 to discuss extent of property still needing to be acquired subsequent to revision of property lines by County GIS/Land Records personnel.

Jan 2021Jan 2021Feb 2021Jul 2021Jan 2022Design/ROW67
$590,000.00
Click Here for More DetailsFleischer, David14.08/3/2020 1:43 PM
35

​Sidewalk Gaps

John Paces-WilesPickett Rd, Leon St, Hunt St, Cheek Rd, South Elm St, Lumley Rd, and East Club Blvd.
$1,255,600.00

PM: 90% design submittal was received on May 8, 2020. Property acquisition to run into October, followed by utility relocations. Project is scheduled to bid in March 2021. 

RE: Real Estate Officer has contacted all property owners. Currently working with Durham Public Schools to negotiate or determine decision as to landscaping at Brogden Middle School.

Nov 2020Oct 2020Feb 2021Jul 2021Nov 2021Design/ROW64
$1,105,600.00
Click Here for More DetailsFleischer, David15.08/3/2020 1:41 PM
36
EB-5837

Third Fork Creek Phase 2 Trail

John Paces-WilesSouthern Boundaries Park to the American Tobacco Trail
$4,462,670.00

​This bicycle and pedestrian trail will be approximately 1.7 miles long. It will extend Phase I of the Third Fork Creek Trail that was built in 2009 and currently ends at Southern Boundaries Park. The new Phase II trail, identified in the City's Trails and Greenways Master Plan, will extend from Southern Boundaries Park north to the American Tobacco Trail. The new extension will connect users to an existing trail network, surrounding neighborhoods, Weaver Street Recreation Center, Weaver Street Park, Cornwallis Rd, and the American Tobacco Trail.

Prelimanary design is underway. The 30% design submittal is expected in early September. Staff anticipates taking a design amendment to City Council for approval for additional work associated with the final trail alignment not included in the original scope. 

The project as proposed is over budget and in need of additional federal funding currently estimated at $3.5M. Staff intends to apply for additional funds at 65% design. 

Jan 2023April 2023April 2024Design33
$1,608,670.00
$2,854,000Transportation Alternative ProgramApril 2018
Project WebsiteClick Here for More DetailsPaces-Wiles, John15.07/31/2020 3:59 PM
37
EB-5904

Durham Belt Line Trail EB-5904

Nia RodgersDowntown Durham to Avondale Drive
$8,900,000.00

Design proposal and fees are under review with NCDOT.

January 2021September 2018 Fall 2021Fall 2023Planning75
$4,800,000.00
4100000TAPSeptember 11, 2017
General Services department project website.Click Here for More DetailsRodgers, Nia3.02/25/2020 12:53 PM
38

Priority Based Budgeting Bus Shelters

Lauren DavisVarious Locations
$396,000.00

​​Design, Bidding, and Construction related to bus shelters at locations selected via the Priority Based Budgeting process.

2/2020 - Horvath was selected for professional engineering design services. Notice to Proceed is anticipated 3/2020.

TBDTBDTBDTBDTBDPlanning90
Click Here for More DetailsTaylor, Brian7.02/3/2020 10:09 AM
14
SW-66

​Sidewalk

Kitty ThomasW Corporation, Old Oxford Rd, Holloway St, Hillsborough Rd, Clayton Rd, Freeman Rd
$500,000.00

​PW: The project is in acquisions.

RE:
W Corporation, Old Oxford Rd & Holloway St are not yet in acquisition phase.
CLAYTON-FREEMAN:
Real Estate Officer has signed all of the 23 properties needed for this project. Negotiations are in process remainder and closings are in progress (20 of 23 are closed). 
HILLSBOROUGH ROAD: 
Real Estate Officer has signed 11 of 14 properties needed for this project. RE is waiting for PW to answer questions from property owners on the remaining three: McDonalds and CVS need reassurance as to any possible business interruption and other questions. Motel 6 owner has asked to meet PW on site; meeting not yet scheduled.


June 2019July 2020August 2020Jan 2021May 2022Design/ROW80
Click Here for More DetailsFleischer, David8.08/3/2020 2:22 PM
39
SW-69 (Bike Walk Phase III)
  1. ​Neal Road at Constitution
  2. University Drive (Steele to Woodridge)
  3. Shannon (MLK)
  4. McGhehee (Vesson to Chapel Hill)
New Sidewalk - Close Existing Gaps

December 2019-​Held community meetings as advisory meetings to alert residents this project is coming to their neighborhood.




Feb 1, 2022
Click Here for More DetailsTaylor, Brian3.03/2/2020 1:40 PM
40

NEW CITY MANAGED PROJECT - PEDESTRIAN CROSSING

FROM NCDOT LIST TO TRANSPORTATION/PW JOINT EFFORT


Carolina Theatre Pedestrian Crossing
$20,000.00

Updated Design to be provided by Transportation to PW.  No Encroachment Agreement necessary per JES (District Engineer). Ornamental Materials have been delivered to SASS.
March 2020August 2020Pre-Construction
Click Here for More DetailsNicholas, Peter6.07/6/2020 2:27 PM