Project Description
  
  
Monthly Update
  
  
  
  
  
  
  
  
  
  
  
History
  
  
  
Sum= $59,603,743.00Sum= $18,787,794.00
1
EB-4707BN/A

Bike Lanes and Sidewalk; Roundabout at Pope Road

​​Old Durham/Old Chapel Hill Rd: Garrett Road to Pope Road
$7,499,897.00
May 5, 2019 Update:  The final layer of asphalt has been put down. NCDOT is currently installing thermoplastic pavement markings and expects that the project will be substanitally complete by the end of May.

City and DCHC MPO staff have received requests for lighting at the Pope Road roundabout; but that location is outside of the City of Durham limits and is also not in Chapel Hill's limits (NCDOT and the County typically do not provide streetlights on secondary roads, but NCDOT is reportedly reconsidering this policy).  Lighting of the Mt. Moriah Road roundabout, as well as lighting along the corridor up to Garrett Road, is being addressed by a lighting project ordered from Duke Energy by the Transportation Department.  City and NCDOT staff have also received requests that the roundabouts be landscaped, and it is our understanding that Council Member Reece is discussing this with appropriate staff in the General Services Department.
N/AN/A2017-052017-062019-05Construction89.63
$1,197,979.00
$5,999,918 federal  ($302,000 state)STP-DA (PE, ROW, CON); TAP-DA (ROW, CON)February 2008; Supplemental July 2017; Supplemental May 2019

​DCHC MPO Feasibility Study completed in February 2006

Dale McKeelClick hereClick Here for More Details
2
U-4726HOSW-44

Bike Lanes and Sidewalk

​Carpenter Fletcher Rd: Woodcroft Pkwy to Alston Ave
$4,688,983.00
PW: An agenda item is being submitted on August 20 for approval at the September 16 City Council meeting for sewer line relocation design, culvert endwall design, and real estate acquisition services. The Supplimental Agreement submitted by Tranportation must be approved prior to proceeding to request ROW Authiorizaiton. The plans are nearign the 90% stage subject to the additional design needed.  Awaiting the execution of the Railroad Agreement which could cause delays. 
2019-12 (Dec 2018)May 2021 (June 2019)   July 2021 (March 2020)  Dec 2021 (Aug 2020)April 2023 (Dec 2021) Design/ROW83
$1,157,930.00
$3,531,053.00STP-DA (PE, ROW, CON)July 2015

​SEPI Engineering awarded the Design Contract.

David CatesClick hereClick Here for More Details
3
U-4724SW-45

Bike Lanes and Sidewalk

Cornwallis Rd: S. Roxboro St to Chapel Hill Rd
$5,432,020.00

 PW: An agenda item is being submitted on August 20 for approval at the September 16 City Council meeting for utiltiy design services and real estate acquisition services. Then the 65% plans can be completed. 

April 2020November 2020October 2021Mar 2022July 2023Design/ROW60
$1,214,867.00
$4,217,153.00STP-DA (PE, CON)June 2015

Alta Engineering was awarded the Design Contract.

Neil AllenClick hereClick Here for More Details
4
U-4726HNSW-46

Sidepath/Bike Lanes and Sidewalk

Hillandale Rd: I-85 to NC 147
$3,107,941.00

 PW: Expecting to receive the 90% plans from the cosnsultant the week of August 19. The consultant acquisiton contract has been executed. Submitting the ROW Authorization to NCDOT the week of August 19. Awaiting the execution of the Railroad Agreement which could cause delays. 

Jan 2020 (Nov 2018)June 2021 (May 2019) Aug 2021 (Feb 2020) Jan 2022 (July 2020) Mar 2023 (Sept 2021)Design/ROW85
$817,442.00
$2,290,499.00STP-DA (PE, ROW, CON)June 2015

Ramey Kemp was awarded the Design Contract.

 

David CatesClick hereClick Here for More Details
5
C-4928SW-47

Bike Lanes and Sidewalk

​Morreene Rd: Erwin Rd to Neal Rd
$6,317,129.00

 PW: Submitted the 90% plans into DSC for Transportation’s re-review. Executed the design and real estate professional services contract amendment. Submitting the ROW Authorization request the week of August 19.

Jan 2020 (Nov 2018)May 2021 (June 2019) July 2021 (Feb 2020) Dec 2021 (July 2020) April 2023 (Nov 2021) Design/ROW75
$1,418,418.00
$4,898,711.00STP-DA (PE, ROW, CON); CMAQ (CON)June 2015

​Kimley Horn was awarded the Design Contract.

 

David CatesClick hereClick Here for More Details
6
C-5183BSW-40

Sidewalk

​Alston Ave: Capps Street to Riddle Road
$913,339.00

PW: Public Works is pursuing a Stream Buffer permit based on a stream identified in a the categorical exclusion report .  All other permits are aquired to proceed.  The stream buffer permit is only needed before construction can begin. There will not be an impact to the existing timeline.

PW: Public Works is working toward a Construction Authorization date of September 30, 2019. The PS&E documetns will be submitted the week of August 19. 

RE: Real estate activity is complete. Right of Way Certification received from NCDOT on 5/2.

2017-082018-102019-09 (2019-07)2020-05 (2020-01)2021-04 (2020-09)Design/ROW100
$268,979.00
$644,360.00CMAQ (CON); *AMENDMENT TO ADD ROWOctober 2016
Mr. Kitty ThomasClick hereClick Here for More Details
7
EB-5514SW-39

Bike Lanes (Hope Valley to Cornwallis) and Sidewalk

University Dr: Chapel Hill Rd to Cornwallis Rd
$1,586,063.00

PW: Construction is underway and on schedule. Several utility conflicts are being encountered and filed adjstments made. A potential conflict to completion of the project on time is the overhead relocation of utiltiies, which is being delayed by Frontier.

2015-04Dec 2017 ***Dates previously adjusted*** (Sept 2017 - Determining how to Condemn for Duke Energy)Oct 2018 ***Dates previously adjusted*** (July 2018 Determining how to Condemn for Duke Energy)Mar 2019 ***Dates previously adjusted*** (Dec 2018 Determining how to Condemn for Duke Energy)Jan 2020 ***Dates previously adjusted*** (July 2019 Determining how to Condemn for Duke Energy)Construction45
$561,063.00
$820,000 federal ($205,000 state)STP-EB (CON)December 2014
Neil AllenClick hereClick Here for More Details
8
EB-5703SW-52

Sidewalk (both sides Kangaroo to Hillsborough, one side Hillsborough to Sprunt)

 

LaSalle St: Kangaroo Dr to Sprunt Ave
$742,232.00
PW: The 90% plans are beign prepared. Awaiting the execution of the Railroad Agreement which could cause delays. A Suppliment Agreement needs to be executed to add the ROW Work Task-Code. Then the ROW Authorzation can be approved.  
Jan 2020 (Mar 2019) Dec 2021 (Sept 2019) Feb 2022 (June 2020)  July 2022 (Nov 2020) Sept 2023 (Jan 2022)  Design54
$204,552.00
$537,680.00TAP (PE, CON)August 2016

​Sepi was awarded the Design Contract.

David CatesClick hereClick Here for More Details
9
EB-5704SW-53

Sidewalk (one side)

Raynor St: N Miami Blvd to Hardee St
$364,435.00
PW: Plans are at 100%  and need sign off. A Suppliment Agreement needs to be executed to add the ROW Work Task-Code. Then the ROW Authorzation can be approved.  
June 2019 (Jan 2019) Feb 2021 (July 2019) April 2021 (April 2020) Sept 2021 (Sept 2020) Aug 2022 (Aug 2021) Design/ROW95
$100,435.00
$264,000.00TAP (PE, CON)August 2016

​Ramey-Kemp was awarded the Design Contract.

Neil AllenClick hereClick Here for More Details
10
EB-5715SW-50

Sidewalk (east side)

North Duke St: Murray Ave to Roxboro Rd
$1,608,372.00

PW: 90% plans submitted to public works engineering for third review. A Suppliment Agreement needs to be executed to add the ROW Work Task-Code. Then the ROW Authorzation can be approved.  

Oct 2019 (Feb 2019)Sept 2021 (Oct 2019)  Nov 2021 (July 2020)  April 2022 (Dec 2020)  June 2023 (Feb 2022)Design/ROW70
$443,252.00
$1,165,120.00TAP (PE, CON)August 2016

Kimley-Horn was awarded the Design Contract. 

Neil AllenClick hereClick Here for More Details
11
EB-5708SW-51

Sidewalk (south side)

NC 54: NC 55 to City Limits
$364,435.00

PW: Executed the design and real estate professional services contract amendment. The 90% plans are in review by Public Works. A Suppliment Agreement needs to be executed to add the ROW Work Task-Code. Then the ROW Authorzation can be approved.  

2020-02 (Jan 2019)Jan 2022 (July 2019) Mar 2022 (April 2020) Aug 2022 (Sept 2020) July 2023 (Aug 2021)Design/ROW76
$34,435.00
$330,000.00SRTS (PE, CON)August 2016

Davenport ​was awarded the Design Contract.

David CatesClick hereClick Here for More Details
12
N/ASW-41

Sidewalk

N Roxboro Rd: Pacific Ave to Murray Ave
$445,000.00

PW: The project is in acquisition.

RE: 31 properties to acquire. 28 owners have provided Options to Purchase to the City. Closings with owners cannot commence as PW has indicated that a plat cannot be prepared for recordation until return of Charles Wagner and his subsequent review. Expected late-September or early-October. 

Aug 2017Oct 2019 (February, 2019)Feb 2020July 2020 June 2021Design/ROW80
$445,000.00
N/AN/AN/A
Mr. Kitty ThomasClick Here for More Details
13
N/ASW-66
Sidewalk B+W I
Clayton and Freeman Road
$203,000.00

​PW: In review & permitting process

May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$203,000.00
N/AN/AN/A
Tim WatsonClick hereClick Here for More Details
14
N/ASW-66
Sidewalk B+W I
Hillsborough Road: LaSalle to Neal/Bus Stop
$380,000.00

PW: In review & permitting process

May 2019 (was Jan 2019)July 2019March 20202020-08December 2021Design85
$380,000.00
N/AN/AN/A
Jeanie JamesClick hereClick Here for More Details
15
N/ASW-66
Sidewalk B+W I
Holloway Street: Gary to Guthrie
$487,500.00

PW: In review & permitting process

May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$487,500.00
N/AN/AN/A
Kyle PhinneyClick hereClick Here for More Details
16
N/ASW-66
Sidewalk B+W I
Old Oxford Road: Dearborn to Roxboro
$206,250.00

PW: In review & permitting process
May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$206,250.00
N/AN/AN/A
Tim WatsonClick hereClick Here for More Details
17
N/ASW-66
Sidewalk B+W I
Corporation St: North Duke St to Mangum
$310,000.00

PW: In review & permitting process
May 2019 (was January 2019)July 2019March 20202020-08December 2021Design85
$310,000.00
N/AN/AN/A
Kevin ZelayaClick hereClick Here for More Details
18
C-5605EBicycle Lane Striping

Bike Lanes

8 Miles
$829,170.00
Consultant is preparing final design package for NCDOT review.  Signal plans are underway.  CE document has been approved.  Municipal agreement has been fully executed.





May 2019 (December date adjusted due to staff vacancies)N/ASeptember 2019 (April date adjusted due to staff vacancies)February 2020 (September date adjusted due to staff vacancies)May 2020 (December date adjusted due to staff vacancies)Design95
$165,834.00
663,336.00CMAQTBD
Ellen Beckmannhttp://durhamnc.gov/3606/2018-Bicycle-ImprovementsClick Here for More Details
19
C-5605IDurham Neighborhood Bike Route

Bike Lane/Bike Boulevard

7 Miles
$631,873.00

Public Meeting held December 11th on proposed routes and concept designs. More detailed engineering and categorical exclusion work underway.

Door hangers placed at all properties on proposed routes in early February.  Postcard mailed to all property owners of record in early February.  Residents requested to contact city staff with questions or comments and fill out an on-line feedback form.

As of March 4, 2019, city staff have been contacted by a handful or residents and more than 100 have completed the on-line feedback form.

The Environmental Document (CE) and Right-of-Way Plans Complete (RPC) are scheduled to be completed by 3/29/19.
July 2019 (October 2018 date adjusted due to NCDOT review times)N/ASeptember 2019 (January 2019 adjusted due to delay in design phase)November 2019 (May 2019 date adjusted due to delay in design phase)April 2020 (October 2019 date adjusted due to delay in design phase)Design50
$126,375.00
$505,498.00CMAQOctober 10, 2017
Dale McKeelhttp://durhamnc.gov/3763/Neighborhood-Bike-RoutesClick Here for More Details
20
EB-5834SW-72

Sidewalks (both sides)

Guess Road: Hillcrest Drive to West Carver Street
$1,103,803.00

Project is on hold

$375,803.00
728,000.00Transportation Alternatives Program (TAP)
TransporationClick Here for More Details
21
SW-70

Bike+Walk Sidewalk 2019

Cooper, Morehead, University, Lakewood, Carlton, Queen, Lawson, Hilllandale, Seminary, Murray, Sima
$400,000.00
PW: The project is under construction beginning at Morehead Avenue.
NANA2018-122018-042020-02Construction5
Mr. Kitty ThomasClick Here for More Details
22
NASW-67

​Sidewalk Repair 2019

Various locations
$1,420,000.00

​PW: The Agenda memo for construciton award was submitted for City Council approval on September 3, 2019.

NANAApril 2019October 2019November 2020Pre-Construction80
NANANA
Kitty ThomasClick Here for More Details
23
N/ASW-68

Sidewalk B+W II


Southwest Durham Drive- 3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

Jeanie JamesClick Here for More Details
24
N/ASW-68

Sidewalk B+W II


Fulton Street-Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

Kyle PhinneyClick Here for More Details
25
N/ASW-68

Sidewalk B+W II


Broad Street-Installing sidewalk between Hillcrest Drive and Forest Road.

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Installing sidewalk between Hillcrest Drive and Forest Road.

Kyle PhinneyClick Here for More Details
26
N/ASW-68

Sidewalk B+W II


Holt School- In front of Holt School and north to Valley Drive.

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Kevin ZelayaClick Here for More Details
27
N/ASW-68

Sidewalk B+W II


North Pointe-Connect existing sidewalk between McDonalds and Red Roof Inn.

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Tim WatsonClick Here for More Details
28
N/ASW-68

Sidewalk B+W II


Fayetteville-From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

Kyle PhinneyClick Here for More Details
29
N/ASW-68

Sidewalk B+W II


Stadium Drive-From Olympic to Duke Street

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From Olympic to Duke Street

Kevin ZelayaClick Here for More Details
30
N/ASW-68

Sidewalk B+W II


Raynor Steet - ​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

​August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

Jeanie JamesClick Here for More Details
31

2019 Signalizede Pedestrian Improvements

1. Arnette Avenue and Morehead Avenue 2. Driver Street and East Main Street 3. East Lawson Street and Lincoln Street 4. East Lawson Street and Merrick Street 5. East Main Street and Dillard Street 6. West Markham Avenue and Washington Street
$350,000.00
June 2019June 2019July 2019September 2019April 2020Design70%
Click Here for More Details
32

HUD Pedestrian Upgrades

C-0166 Lawson St. at Ridgeway Ave. C-0063 Bacon St. at Pettigrew St. 05-1967 SR 1118 (Fayetteville St.) at Cecil St.   05-0333 NC 98 at Adams St. 05-1032 NC 55 (Avondale Dr.) at Trinity Ave. 05-1031 NC 55 (Avondale Dr.) at Markham Ave.  05-0271 US 70 Bus.
$600,000.00
June 2019June 2019July 2019September 2019June 2020Design90%
Click Here for More Details
33
EB-5720

R. Kelly Bryant Bridge Trail


NC55 at Dakota Street to Drew Granby Park
$5,414,031.00

​​This bicycle and pedestrian trail will be approximately 3 miles long. It will connect the existing Rocky Creek Trail on Dakota Street north to the Drew/Granby Park located on Drew Street in Durham. The trail will connect users to an existing trail network, surrounding neighborhoods, NC Highway 55, Burton Park, Burton Elementary School, the 147 blue pedestrian bridge, Eastway Elementary Schoo, East End Park, Long Meadow Park, Drew/Granby Park.

July 2022October 2022Design0
$1,424,410.00
$3,989,621.00Transportation Alternative ProgramSeptember 2017, April 2018
Jessica KempProject WebsiteClick Here for More Details
34

​Sidewalk (west side), cross walks and bus stop amenities

Chapel Hill Rd: Morehead Ave to W. Lakewood Ave.
$590,000.00

The site assessment is complete, and design is underway. The 20% submittal anticipated in mid-October.

June 2020July 2020July 2020December 2020December 2021Design/ROW18
$590,000.00

Horvath was selected as the designer through RFQ.

John Paces-WilesClick Here for More Details
35

​Sidewalk Gaps

Pickett Rd, Leon St, Hunt St, Cheek Rd, South Elm St, Lumley Rd, and East Club Blvd.
$1,105,600.00

Site investigation and survey work is underway. The 20% design submittal anticpated in late October.

April 2020October 2020June 2021October 2021March 2022Design/ROW4
$1,105,600.00
John Paces-WilesClick Here for More Details
36
EB-5837

Third Fork Creek Trail - Phase II​

Southern Boundaries Park to the American Tobacco Trail
$3,602,670.00

​This bicycle and pedestrian trail will be approximately 1.7 miles long. It will extend Phase I of the Third Fork Creek Trail that was built in 2009 and currently ends at Southern Boundaries Park. The new Phase II trail identified in the City's Trails and Greenways Master Plan, will extend from Southern Boundaries Park north to the American Tobacco Trail. The new extension will connect users to an existing trail network, surrounding neighborhoods, Weaver Street Recreation Center, Weaver Street Park, Cornwallis Rd, and the American Tobacco Trail.

July 2022October 2022September 2023Design0
$748,670.00
$2,854,000.00Transportation Alternative ProgramApril 2018
Jessica KempProject WebsiteClick Here for More Details
37
EB-5904

Durham Belt Line Trail EB-5904

Downtown Durham to Avondale Drive
$8,900,000.00

Reviewing qualifications of NCDOT qualified firms submitting LOIs.

January 2021September 2018July 2021Dec 2022Planning75
$4,800,000.00
4100000TAPSeptember 11, 2017
Nia RodgersGeneral Services department project website.Click Here for More Details