Project Description
  
  
Monthly Update
  
  
  
  
  
  
  
  
  
  
  
History
  
  
  
  
  
  
Sum= $59,040,536.00Sum= $17,285,753.00
1
EB-4707BN/A

Bike Lanes and Sidewalk; Roundabout at Pope Road

​​Old Durham/Old Chapel Hill Rd: Garrett Road to Pope Road
$7,499,897.00
May 5, 2019 Update:  The final layer of asphalt has been put down. NCDOT is currently installing thermoplastic pavement markings and expects that the project will be substanitally complete by the end of May.

City and DCHC MPO staff have received requests for lighting at the Pope Road roundabout; but that location is outside of the City of Durham limits and is also not in Chapel Hill's limits (NCDOT and the County typically do not provide streetlights on secondary roads, but NCDOT is reportedly reconsidering this policy).  Lighting of the Mt. Moriah Road roundabout, as well as lighting along the corridor up to Garrett Road, is being addressed by a lighting project ordered from Duke Energy by the Transportation Department.  City and NCDOT staff have also received requests that the roundabouts be landscaped, and it is our understanding that Council Member Reece is discussing this with appropriate staff in the General Services Department.
N/AN/A2017-052017-062019-05Construction89.63
$1,197,979.00
$5,999,918 federal  ($302,000 state)STP-DA (PE, ROW, CON); TAP-DA (ROW, CON)February 2008; Supplemental July 2017; Supplemental May 2019

​DCHC MPO Feasibility Study completed in February 2006

Dale McKeelClick hereClick Here for More DetailsTaylor, Brian1.08/29/2019 2:22 PM
2
U-4726HOSW-44

Bike Lanes and Sidewalk

​Carpenter Fletcher Rd: Woodcroft Pkwy to Alston Ave
$4,688,983.00
PW: An agenda item was approved for sewer line relocation design, and culvert endwall design. The plans are at the 90% stage.
2019-12 (Dec 2018)May 2021 (June 2019)   July 2021 (March 2020)  Dec 2021 (Aug 2020)April 2023 (Dec 2021) Design/ROW83
$1,157,930.00
$3,531,053.00STP-DA (PE, ROW, CON)July 2015

​SEPI Engineering awarded the Design Contract.

David CatesClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:39 PM
3
U-4724SW-45

Bike Lanes and Sidewalk

Cornwallis Rd: S. Roxboro St to Chapel Hill Rd
$5,432,020.00

 PW: Work is underway to complete the 65% plans. 

April 2020November 2020October 2021Mar 2022July 2023Design/ROW60
$1,214,867.00
$4,217,153.00STP-DA (PE, CON)June 2015

Alta Engineering was awarded the Design Contract.

Neil AllenClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:34 PM
4
U-4726HNSW-46

Sidepath/Bike Lanes and Sidewalk

Hillandale Rd: I-85 to NC 147
$3,107,941.00

 PW: The consultant is working on the 100% design plans.

Jan 2020 (Nov 2018)June 2021 (May 2019) Aug 2021 (Feb 2020) Jan 2022 (July 2020) Mar 2023 (Sept 2021)Design/ROW85
$817,442.00
$2,290,499.00STP-DA (PE, ROW, CON)June 2015

Ramey Kemp was awarded the Design Contract.

 

David CatesClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:40 PM
5
C-4928SW-47

Bike Lanes and Sidewalk

​Morreene Rd: Erwin Rd to Neal Rd
$6,317,129.00

 PW: The 100% design plans are under review.

Jan 2020 (Nov 2018)May 2021 (June 2019) July 2021 (Feb 2020) Dec 2021 (July 2020) April 2023 (Nov 2021) Design/ROW75
$1,418,418.00
$4,898,711.00STP-DA (PE, ROW, CON); CMAQ (CON)June 2015

​Kimley Horn was awarded the Design Contract.

 

David CatesClick hereClick Here for More DetailsVenable, Ed2.010/7/2019 12:48 PM
6
C-5183BSW-40

Sidewalk

​Alston Ave: Capps Street to Riddle Road
$913,339.00

PW: Public Works is responding to NCDOT comments arising from the submitted Construction Authorization. The edits are largelly related to the project manaual of the PS&E package. 


2017-082018-102019-11 (2019-07)2020-05 (2020-01)2021-04 (2020-09)Pre-Construction50
$268,979.00
$644,360.00CMAQ (CON); *AMENDMENT TO ADD ROWOctober 2016
Mr. Kitty ThomasClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 12:59 PM
7
EB-5514SW-39

Bike Lanes (Hope Valley to Cornwallis) and Sidewalk

University Dr: Chapel Hill Rd to Cornwallis Rd
$1,586,063.00

PW: Construction is underway. There have been several delays that will extend the proejct due to a gas line conflict. We hope to begin a field resolution of the gas line conflict in mid-Nov.

2015-04Dec 2017 ***Dates previously adjusted*** (Sept 2017 - Determining how to Condemn for Duke Energy)Oct 2018 ***Dates previously adjusted*** (July 2018 Determining how to Condemn for Duke Energy)Mar 2019 ***Dates previously adjusted*** (Dec 2018 Determining how to Condemn for Duke Energy)Jan 2020 ***Dates previously adjusted*** (July 2019 Determining how to Condemn for Duke Energy)Construction60
$561,063.00
$820,000 federal ($205,000 state)STP-EB (CON)December 2014
Neil AllenClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:32 PM
8
EB-5703SW-52

Sidewalk (both sides Kangaroo to Hillsborough, one side Hillsborough to Sprunt)

 

LaSalle St: Kangaroo Dr to Sprunt Ave
$742,232.00
PW: The 90% plans are beign prepared.
Jan 2020 (Mar 2019) Dec 2021 (Sept 2019) Feb 2022 (June 2020)  July 2022 (Nov 2020) Sept 2023 (Jan 2022)  Design54
$204,552.00
$537,680.00TAP (PE, CON)August 2016

​Sepi was awarded the Design Contract.

David CatesClick hereClick Here for More DetailsVenable, Ed2.010/7/2019 12:49 PM
9
EB-5704SW-53

Sidewalk (one side)

Raynor St: N Miami Blvd to Hardee St
$364,435.00
PW: 100% Plans, Specifications and Estimates are approved and wwe are waiting on Right of Way Authorization prior to being forwarded to General Services for Right of Way acquisition. 
June 2019 (Jan 2019) Feb 2021 (July 2019) April 2021 (April 2020) Sept 2021 (Sept 2020) Aug 2022 (Aug 2021) Design/ROW95
$100,435.00
$264,000.00TAP (PE, CON)August 2016

​Ramey-Kemp was awarded the Design Contract.

Neil AllenClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:37 PM
10
EB-5715SW-50

Sidewalk (east side)

North Duke St: Murray Ave to Roxboro Rd
$1,608,372.00

PW: The PS&E package was submitted to NCDOT through EBS and we await approval. Once approved we can request ROW authorization. 

Oct 2019 (Feb 2019)Sept 2021 (Oct 2019)  Nov 2021 (July 2020)  April 2022 (Dec 2020)  June 2023 (Feb 2022)Design/ROW70
$443,252.00
$1,165,120.00TAP (PE, CON)August 2016

Kimley-Horn was awarded the Design Contract. 

Neil AllenClick hereClick Here for More DetailsVenable, Ed3.011/4/2019 1:36 PM
11
EB-5708SW-51

Sidewalk (south side)

NC 54: NC 55 to City Limits
$364,435.00

PW: The 90% plans are in review by NCDOT.

2020-02 (Jan 2019)Jan 2022 (July 2019) Mar 2022 (April 2020) Aug 2022 (Sept 2020) July 2023 (Aug 2021)Design/ROW76
$34,435.00
$330,000.00SRTS (PE, CON)August 2016

Davenport ​was awarded the Design Contract.

David CatesClick hereClick Here for More DetailsVenable, Ed2.010/7/2019 12:49 PM
12
N/ASW-41

Sidewalk

N Roxboro Rd: Pacific Ave to Murray Ave
$445,000.00

PW: The project is in acquisition.

RE: Real Estate has procured Options on all properties. Project plat has now been recorded, closings are in process. 

Aug 2017Nov 2019 (February, 2019)Feb 2020July 2020 June 2021Design/ROW80
$445,000.00
N/AN/AN/A
Mr. Kitty ThomasClick Here for More DetailsFleischer, David4.011/4/2019 2:29 PM
18
C-5605EBicycle Lane Striping

Bike Lanes

8 Miles
$1,252,713.00
NCDOT construction authorization was approved in September 2019.  Consultant needs to prepare updated final PS&E package with pavement marking and signal plans.





May 2019 (December date adjusted due to staff vacancies)N/ASeptember 2019 (April date adjusted due to staff vacancies)February 2020 (September date adjusted due to staff vacancies)May 2020 (December date adjusted due to staff vacancies)Design99
$250,543.00
1002170CMAQ2/18/2019
Ellen Beckmannhttp://durhamnc.gov/3606/2018-Bicycle-ImprovementsClick Here for More DetailsBeckmann, Ellen2.011/4/2019 2:45 PM
19
C-5605IDurham Neighborhood Bike Route

Bike Lane/Bike Boulevard

7 Miles
$631,873.00

Public Meeting held December 11th on proposed routes and concept designs. More detailed engineering and categorical exclusion work underway.

Door hangers placed at all properties on proposed routes in early February.  Postcard mailed to all property owners of record in early February.  Residents requested to contact city staff with questions or comments and fill out an on-line feedback form.

As of March 4, 2019, city staff have been contacted by a handful or residents and more than 100 have completed the on-line feedback form.

The Environmental Document (CE) and Right-of-Way Plans Complete (RPC) are scheduled to be completed by 3/29/19.
July 2019 (October 2018 date adjusted due to NCDOT review times)N/ASeptember 2019 (January 2019 adjusted due to delay in design phase)November 2019 (May 2019 date adjusted due to delay in design phase)April 2020 (October 2019 date adjusted due to delay in design phase)Design50
$126,375.00
$505,498.00CMAQOctober 10, 2017
Dale McKeelhttp://durhamnc.gov/3763/Neighborhood-Bike-RoutesClick Here for More DetailsTaylor, Brian1.08/29/2019 2:23 PM
20
EB-5834SW-72

Sidewalks (both sides)

Guess Road: Hillcrest Drive to West Carver Street
$1,103,803.00

Project is on hold

$375,803.00
728,000.00Transportation Alternatives Program (TAP)
TransportationClick Here for More DetailsBeckmann, Ellen2.011/4/2019 2:46 PM
21
SW-70

Bike+Walk Sidewalk 2019

Cooper, Morehead, University, Lakewood, Carlton, Queen, Lawson, Hilllandale, Seminary, Murray, Sima
$400,000.00
PW: The project is under construction.. Work on Seminary Ave, Morehead Ave is complete. Work on Carlton St and Queen St locations was delayed due to rain days but should begin in the first week of November.
NANA2018-122018-042020-02Construction25
Mr. Kitty ThomasClick Here for More DetailsVenable, Ed3.011/4/2019 1:06 PM
22
NASW-67

​Sidewalk Repair 2019

Various locations
$1,420,000.00

​PW: A pre-construction meeting with BridgePoint Civil was held on October 22, 2019. A notice to proceed was issued with an effective date November 4, 2019 for field work start. 

NANAApril 2019Nov 2019November 2020Pre-Construction100
NANANA
Kitty ThomasClick Here for More DetailsVenable, Ed3.011/4/2019 1:02 PM
23
N/ASW-68

Sidewalk B+W II


Southwest Durham Drive- 3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

3 spot connections starting at Old Chapel Hill Road and going north to the northern property line of 3705 SW Durham Drive.

Jeanie JamesClick Here for More DetailsNicholas, Peter5.010/7/2019 2:50 PM
24
N/ASW-68

Sidewalk B+W II


Fulton Street-Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.


August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Widening sidewalk 5' more (10' total) north from Pratt Street to NC-147

Kyle PhinneyClick Here for More DetailsLecky, Jeff2.010/7/2019 2:22 PM
25
N/ASW-68

Sidewalk B+W II


Broad Street-Installing sidewalk between Hillcrest Drive and Forest Road.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Installing sidewalk between Hillcrest Drive and Forest Road.

Kyle PhinneyClick Here for More DetailsLecky, Jeff2.010/7/2019 2:22 PM
26
N/ASW-68

Sidewalk B+W II


Holt School- In front of Holt School and north to Valley Drive.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Kevin ZelayaClick Here for More DetailsLecky, Jeff2.010/7/2019 2:23 PM
27
N/ASW-68

Sidewalk B+W II


North Pointe-Connect existing sidewalk between McDonalds and Red Roof Inn.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

Tim WatsonClick Here for More DetailsLecky, Jeff2.010/7/2019 2:23 PM
28
N/ASW-68

Sidewalk B+W II


Fayetteville-From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From existing sidewalk north of Roxboro to existing sidewalk by Mt. Zion

Kyle PhinneyClick Here for More DetailsLecky, Jeff2.010/7/2019 2:24 PM
29
N/ASW-68

Sidewalk B+W II


Stadium Drive-From Olympic to Duke Street

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

​2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

From Olympic to Duke Street

Kevin ZelayaClick Here for More DetailsLecky, Jeff2.010/7/2019 2:24 PM
30
N/ASW-68

Sidewalk B+W II


Raynor Steet - ​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

October 4, 2019 recieved comments from NCDOT on 3rd review.

October 4, 2019​ revised plans resubmitted for 3rd review to DSC.  On schedule.

September 9, 2019 recieved comments from DSC.

August 8, 2019 revised plans resubmitted for 2nd review to DSC.  On schedule.

June 2020Design60%

2019-06-26 1st Submittal of Plans for Review.  Distributed to City Review as well as Utility Companies.

​From existing sidewalk north of Liberty to existing sidewalk south of Holloway.

Jeanie JamesClick Here for More DetailsLecky, Jeff2.010/7/2019 2:25 PM
31

2019 Signalized Pedestrian Improvements

1. Arnette Avenue and Morehead Avenue 2. Driver Street and East Main Street 3. East Lawson Street and Lincoln Street 4. East Lawson Street and Merrick Street 5. East Main Street and Dillard Street 6. West Markham Avenue and Washington Street
$450,000.00

Awaiting Project Goals from E & I.  Project will be advertised in October 2019.

June 2019 (Actual Design Completion September 2019)N/AJuly 2019 (Actual Advertisement - October 2019)April 2019(Design)                                    December 2020 (Construction)June 2020 (Changed from April 2020)Bid90%
Click Here for More DetailsNicholas, Peter13.011/4/2019 2:28 PM
32

HUD Pedestrian Upgrades

C-0166 Lawson St. at Ridgeway Ave. C-0063 Bacon St. at Pettigrew St. 05-1967 SR 1118 (Fayetteville St.) at Cecil St.   05-0333 NC 98 at Adams St. 05-1032 NC 55 (Avondale Dr.) at Trinity Ave. 05-1031 NC 55 (Avondale Dr.) at Markham Ave.  05-0271 US 70 Bus.
$600,000.00
June 2019June 2019July 2019April 2019(Design)                                    December 2020 (Construction)June 2020Bid95%
Click Here for More DetailsNicholas, Peter4.010/7/2019 2:52 PM
33
EB-5720

R. Kelly Bryant Bridge Trail


NC55 at Dakota Street to Drew Granby Park
$5,414,031.00

​​This bicycle and pedestrian trail will be approximately 3 miles long. It will connect the existing Rocky Creek Trail on Dakota Street north to the Drew/Granby Park located on Drew Street in Durham. The trail will connect users to an existing trail network, surrounding neighborhoods, NC Highway 55, Burton Park, Burton Elementary School, the 147 blue pedestrian bridge, Eastway Elementary School, East End Park, Long Meadow Park, and Drew/Granby Park.

10/2019 - The engineering consultant for this project, Kimley-Horn and Associates, provided an opportunity and constraints analysis of this project for review. Some project alignments would require additional project funding and schedule delays. The City will review and share with residents and interest groups during October and November to collect feedback.

A public event is being held at the Weaver Street Recreation Center 10/29/19 from 5-7:30pm to collect resident input on trail route options. The recretation center is along the project route and mailers and fliers have been distributed in the project area. Spanish translation will be provided.

July 2022October 2022September 2023Design0
$1,424,410.00
$3,989,621.00Transportation Alternative ProgramSeptember 2017, April 2018
Jessica KempProject WebsiteClick Here for More DetailsKemp, Jessica3.010/28/2019 4:11 PM
34

​Sidewalk (west side), cross walks and bus stop amenities

Chapel Hill Rd: Morehead Ave to W. Lakewood Ave.
$590,000.00

The site assessment is complete, and design is underway. The 20% submittal is under review. The 60% submittal is anticipated in mid-January, 2020.

June 2020July 2020July 2020December 2020December 2021Design/ROW34
$590,000.00
John Paces-WilesClick Here for More DetailsPaces-Wiles, John3.010/31/2019 3:19 PM
35

​Sidewalk Gaps

Pickett Rd, Leon St, Hunt St, Cheek Rd, South Elm St, Lumley Rd, and East Club Blvd.
$1,105,600.00

Site investigation and survey work is complete. The 20% design submittal is under review. The 60% submittal is anticipated in January, 2020.

April 2020October 2020June 2021October 2021March 2022Design/ROW28
$1,105,600.00
John Paces-WilesClick Here for More DetailsPaces-Wiles, John3.010/31/2019 3:20 PM
36
EB-5837

Third Fork Creek Trail - Phase II​

Southern Boundaries Park to the American Tobacco Trail
$3,602,670.00

​This bicycle and pedestrian trail will be approximately 1.7 miles long. It will extend Phase I of the Third Fork Creek Trail that was built in 2009 and currently ends at Southern Boundaries Park. The new Phase II trail identified in the City's Trails and Greenways Master Plan, will extend from Southern Boundaries Park north to the American Tobacco Trail. The new extension will connect users to an existing trail network, surrounding neighborhoods, Weaver Street Recreation Center, Weaver Street Park, Cornwallis Rd, and the American Tobacco Trail.

10/2019 - The engineering consultant for this project, Kimley-Horn and Associates, provided an opportunity and constraints analysis of this project for review. Some project alignments would require additional project funding and schedule delays. The City will review and share with residents and interest groups during the month of October and November to collect feedback.

Staff will present a project update at the PAC 4 meeting 11/9/19 and the PAC 1 meeting 11/16/19.

July 2022October 2022September 2023Design0
$748,670.00
$2,854,000.00Transportation Alternative ProgramApril 2018
Jessica KempProject WebsiteClick Here for More DetailsKemp, Jessica2.010/28/2019 4:10 PM
37
EB-5904

Durham Belt Line Trail EB-5904

Downtown Durham to Avondale Drive
$8,900,000.00

Negotiating proposal and fees with selected design firm

January 2021September 2018 Fall 2021Spring 2023Planning75
$4,800,000.00
4100000TAPSeptember 11, 2017
Nia RodgersGeneral Services department project website.Click Here for More DetailsRodgers, Nia2.011/4/2019 9:43 AM

****NEW****

Priority Based Budgeting Bus Shelters

Various Locations

​​Design, Bidding, and Construction related to bus shelters at locations selected via the Priority Based Budgeting process.

10/28/2019 - General Services advertised a professional services Request for Interest to firms in the SLBE program. Letters are due 11/27/19.

TBDTBDTBDTBDTBDPlanning25
Jessica KempClick Here for More DetailsKemp, Jessica3.010/29/2019 3:50 PM
SW-66

​Sidewalk

W Corporation, Old Oxford Rd, Holloway St, Hillsborough Rd, Clayton Rd, Freeman Rd
$500,000.00

​PW: The project is in acquisions.



June 2019July 2020August 2020Jan 2021May 2022Design/ROW10
Kitty ThomasClick Here for More DetailsVenable, Ed2.011/4/2019 1:13 PM